The information concerning the project:

BT Investors Corporation construction traffic 5.

Project name: Project roads south of Ha Tay province in the form of BT contract.

Agency investment decisions: People's Committee of Ha Tay province

Enterprise Project Development Corporation real estate Cienco 5.

+ The relevant legal basis:

- Decision on 04/3/2008 479/QD-UBND; 480/QD-UBND Decision dated 04/3/2008 of Ha Tay provincial People's Committee approving the detailed planning of the rate 1 / 500 Residential Area Thi Thanh Ha - Cienco 5 and My Hung Urban Area - Cienco 5, Ha Tay province;

- Decision on 25.03.2008 633/QD-UBND Ha Tay provincial People's Committee approving the land use fee payable to the budget of the project Urban Thanh Ha - Cienco 5 and My Hung Urban Area - 5 Cienco Corporation by construction traffic five investment;

- Decision No. 301/QD-UBND on 04/02/2008, Decision No. 302/QD-UBND dated 04/02/2008 of People's Committee of Ha Tay province on approving the plan 1 / 2000 Urban Thanh Ha - Cienco 5 and My Hung Urban Area - Cienco 5, Ha Tay province;

- Decision on 03/12/2007 2288/QD-UBND Ha Tay provincial People's Committee approved the proposed profile investment project in the southern province backbone form of BT and other projects to return BT projects;

- Document No. 1316/BGTVT-KHDT dated 06/3/2008 of the Ministry of Transport on the basis of design evaluation of investment project construction roads south of Ha Tay province in the form of BT contract ;

- Document No. 1740/TTgCP-CN dated 15/11/2007 of the Prime Minister about the investment policy approved by building roads to the south, the road Do Xa - Quan Son, Ha Tay province in the form of contract BT and some auxiliary projects for recovery of capital investment;

+ Investment objectives

- Decision on 18.04.2008 987/QD-UBND of Ha Tay province on the implementation of investment project roads south of Ha Tay province;

- Decision No. 964/QD-UBND dated 17/4/2008, 961/QD-UBND Decision dated 17/4/2008, 963/QD-UBND Decision dated 17/4/2008 of Ha Tay province to allow the construction of new urban area in Ha Thanh A - CIENCO5, Urban Thanh Ha B - CIENCO5, My Hung new urban area - CIENCO5;

+ The content and scale construction

- Total length of the entire project ~ 41.5 km.

- Document No. 1783/UBND-TH on 04/18/2008 Ha Tay provincial People's Committee approved the contents of the contract negotiation BT highway project south of Ha Tay province;

- Within the scope of the district where the road runs through, the formation route will motivate economic development, is the basis for the establishment of industrial zones, new urban area, raising the value of land use and exploitation of the potential Features a large area to date has not been effectively exploited.

- Area of land occupied the entire route: about 245.7 ha

- Design axle load 100kN.

- Cross section line of 40m, 4 lanes: 1 m + 10.5 m + 10.5 m + 1 m 17m +

+ Construction site

- Ha Dong City: Kien Hung commune, Phu Luong;

- Design speed of 60km / h

- Objectives of the project is to build new roads to form the connection from Ha Dong to pass through the southern districts of Ha Tay province to serve the needs of people traveling, reducing the load line Highway 21. This route will also help complete the transportation system of the province, connecting with Highway 1, connected with fourth ring road, Le Trong Tan, convenient transport connection to Hai Phong, Quang Ninh and to the southern provinces.

The route runs through the territory: Ha Dong City, the districts of Thanh Oai, Phu Xuyen, Ung Hoa and includes the local:

- Phu Xuyen: Hong Minh Commune, Trung Tri, Phu Tuc, Hoang Long, Chau Can;

- Ung Hoa District: Commune Phuong Tu, Trung Tu, Hoa Lam, Shen Long, Dai Hung, Kim Street;

- Thanh Oai District: Cu Khe Commune, My Hung, Tam Hung, Thanh Thuy, Thanh Van, New Testament, Dan Hoa, Lien Chau;

+ Control point is defined as follows:

Capital Source

- Starting point: km0 - To Phuc La Cathedral - Van Phu (At the intersection of programming Km1 +526.5 Kien Hung Commune, Ha Dong City);

- End point: Next assignment for the bottom 1A Gie belonging to Chau Can, Phu Xuyen District;

+ Total investment: 5156 billion (excluding interest during project implementation).

+ The project counterpart

- Urban Th

- For advanced capital investors to BT road construction will be obtained from: The own capital, loans and other legal mobilization.

To return to investors Cienco 5 in the construction transfer route running south of Ha Tay, Ha Tay province has allocated land for investors and business investment projects to the Capital Area A new marketing Thanh Ha - CIENCO5, Urban Thanh Ha B - CIENCO5 and My Hung Urban Area - CIENCO5 the Decision approving the detailed construction plan of 1 / 500: 479/QD-UBND 04 days / 3 / 2008, dated 04/3/2008 480/QD-UBND and the decision to allow investment in urban areas of: 964/QD-UBND dated 17/4/2008, 961/QD-UBND 17 / 4 / 2008, dated 17/4/2008 963/QD-UBND, as follows:

- The project shall comply with the BT method. Investors raise capital construction, completed projects and BT capital of PPC reimbursed by revenues from land use fees of urban projects.